Description
Jobs can be stuck in Canceling
state, despite having been cancelled.
This means that the resource they use is never freed up,
and subsequent jobs thus indefinitely show the message:
This job is waiting for resource: <your-resource>
Environment
CI pipelines that use Resource groups.
-
Impacted offerings:
- GitLab Self-Managed
- GitLab Runner
Solution
A workaround is provided in gitlab#467107.
- Update that Rails snippet with the affected pipeline (not job) IDs.
- Launch the Rails console.
- Run your updated Rails snippet.
Cause
The job's state machine does not properly transition it from canceling
to canceled
.
Further details are being investigated, see gitlab#467107.